Abstract

This project aims to the technical advice, research, training and improvement of the development of a synchronization system able to meet the grid code requirements set by the transmission system operators consisting of a solution of a system of network synchronization with power converters in wind power applications.

The objectives attributable to the development of a synchronization system able to meet the grid code requirements set by the transmission system operators, can be summarized in two points:

  1. Get a new PLL structure that may be patentable.
  2. Allow the PLL dynamics change depending on internal or external to the same parameters, without conflicting with other existing designs or patented.

 

 

Local members

Alvaro Luna

PhD. Senior Researcher.

Jose Ignacio Candela

PhD. Senior Researcher. Project Responsible

 

Partnership centers

Technical University of Catalonia (UPC) - BarcelonaTech; Ingeteam Power Technology, S.A
 